Arithmetic Ability
Time and Work

11 / 118

Q.

A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in --- days ?

View Answer

Correct choice: D

Explanation:

A can complete the work in 12 days working 8 hours a day => Number of hours A can complete the work = 12×8 = 96 hours => Work done by A in 1 hour = 1/96 B can complete the work in 8 days working 10 hours a day => Number of hours B can complete the work = 8×10 = 80 hours => Work done by B in 1 hour = 1/80 Work done by A and B in 1 hour = 1/96 + 1/80 = 11/480 => A and B can complete the work in 480/11 hours A and B works 8 hours a day. Hence total days to complete the work with A and B working together = (480/11)/ (8) = 60/11 days
11 / 118