Toggle navigation
Home
Study Room
AP Eamcet Engineering Online Mock Exams
AP Eamcet Medical Online Mock Exams
Exams
Features
Pricing
Login
Register
Study Room
Study Room
Arithmetic Ability
Lessons
Alligation or Mixture
Area
Average
Banker's Discount
Boats and Streams
Calendar
Chain Rule
Clocks
Compound Interest
Decimal Fractions
HCF and LCM
Height and Distance
Logarithms
Numbers
Odd Man Out and Series
Partnership
Percentage
Permutations and Combinations
Pipes and Cistern
Probability
Problems on Ages
Problems on Numbers
Problems on Trains
Profit and Loss
Races and Games
Ratio and Proportion
Simple Interest
Simplification
Square Roots and Cube Roots
Stocks and Shares
Time and Distance
Time and Work
True Discount
Volume and Surface Area
Goto
Arithmetic Ability
Chain Rule
Take Exam
01
02
03
04
05
06
07
08
09
10
11
12
13
14
Previous
14 / 14
Next
Q.
A certain number of men can finish a piece of work in 100 days. If there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally?
A.
75
B.
82
C.
100
D.
110
View Answer
Correct choice: D
Explanation:
Originally let there be x men. Less men, More days (Indirect Proportion) Therefore, (x-10) : x :: 100 :110 => (x - 10) * 110 = x * 100 => x= 110